Next week the modular units from Olympic Heights School will begin to be relocated to their new home. At this time, you can expect the following:  

  • The week of May 5, two modular units will be detached from their current site (connected to the school) and moved to the south section of the school field where they will be fenced off for safety reasons.  
  • Between May 27 – 30, the remaining two units will be detached from their sites and moved to the same portion of the school field as the first two units. All four units will be fenced off.  
  • Removal of the four modular units from the field will take place during the week of June 2 with the units moved overnight to their new home.  
  • In June, after the modular units are fully removed, the asphalt area will be repaved, and any landscaping remediation will be completed. 

Student and staff safety remains our top priority. The construction area will be securely fenced, and all work during school hours will be carefully managed to minimize disruptions.  

Thank you for your patience and support as we make these improvements to provide additional learning spaces across our growing school system. 

If you have any questions or concerns, please contact  facilityprojects@cbe.ab.ca